F-35 Over Budget and Behind Schedule

BY Herschel Smith
15 years, 6 months ago

Matthew Potter has penned a very important article at BNET concerning the F-35.  I will cite it at length.

Veteran newspaper reporter George C. Wilson asked in a recent column that appeared in CongressDaily why rush the F-35 into production? In that gentleman’s eyes the program is experiencing delays in testing and development as well as overall cost to product and operate. In Wilson’s view it might make sense to save the whole $298 billion planned to procure the F-35 since there may not be the necessary threat to justify its purchase.

Wilson compares the F-35 to a similar program from the 1960’s where an attempt was made to develop one aircraft for the U.S. Air Force and Navy. This TFX program did result in the F-111 supersonic bomber used by the Air Force and Australia. The Navy rejected the aircraft and went on to purchase the F-14 Tomcat long range fighter. The F-111 had a drawn out development and the desire to have it due multiple missions for different services increased this and the cost increases reflected this.

In the upcoming 2011 defense budget the F-35 program will be restructured again to delay production and extend development. Money will have to be reprogrammed from buying aircraft to paying for this development extension. Lockheed Martin (LMT) the lead contractor on the program has offered up taking some money out of its fee from the development phase but the extended production run will only add money to the back end. Lockheed will make up some of the money lost in 2011 – 2013 through these quantities.

Of course the question to ask if Wilson’s suggestion was acted on would be what to do for a new fighter? The F-35 is it. It will replace F-16, A-10, F-18 and AV-8 aircraft in service with the U.S. Air Force, Marines, Navy and allied inventories. The F-22 is a purer, long range fighter that was supposed to replace the F-15. Now less then 200 will be built and they cannot supplant the large numbers of other aircraft. It also doesn’t exist in a carrier based version so it cannot do the F-18 or AV-8 mission. There had been attempts to restart the F-15 production line in the early part of this decade but nothing came of that. Perhaps the F-18E/F/G could be built for the Air Force as well as the Navy and Marines?

So if an existing aircraft cannot be produced to replace the aging F-16, F-18 and AV-8 force then a new replacement program will have to be started. Even if there are no advanced requirements but a straight replacement there will be the great cost of beginning again a development program and ramping up a production capability. It would also make little sense in building a new aircraft without adding advances in sensors, weapons, survivability and electronics. This will increase the cost to both produce and operate the aircraft.

I know one officer whose way was paid through the Air Force Academy, who trained other fighter pilots for several years, and who now wears shorts and a polo shirt and works on finish carpentry every day for his base because the Air Force has no fighter for him to fly and nothing else for him to do.  The existing fleet of aircraft is aging.  This means that stress corrosion cracking and fatigue on structural members and rotating parts has begun to take its toll.  Aircraft cannot fly forever, and while it was in vogue to bash the F-22 several months ago, remember what The Captain’s Journal said.

Basically, this amounts to crafting a model of hybrid wars as the primary mission (along with jettisoning the two-war paradigm under the QDR), and telling the Air Force to plan for it.  This is circular, and proves little if anything regarding whether the F-22 is needed.  It may not matter, since Obama has apparently won this victory, calling the F-22 wasteful and threatening a veto of any legislation that includes more F-22s …

The Captain’s Journal would feel better about the F-35 as the next generation all purpose fighter aircraft if it had seen production and flying hours.  But it is inferior in air-to-air combat and yet to be flown by U.S. AF pilots.  Also note that in spite of what the QDR might conclude, we have recommended replacement of the sea-based expeditionary model for forcible entry with a combined sea-based and air-based approach that doesn’t rely on the Expeditionary Fighting Vehicle.

We have recommended heavier reliance, not less reliance, on manned air power both from land bases and sea-based craft as an important leg of conventional, expeditionary, counterinsurgency and hybrid warfare.  We will grant the point that the VTOL F-35 will be a mainstay in the Marines’ model rather than the F-22, but if the skies are controlled by rockets and enemy aircraft, the sinking of an Amphibious Assault Dock with an entire Battalion of Marine infantry on board would end whatever expeditionary entry that was planned.  Air power is critical to the success of every form of warfare mentioned above.

It may be that the F-35 will come along in time to contribute to interim needs, and that its inferiority to the F-22 won’t do harm to the conduct of its mission.  But this hasn’t been proven to our standards.

I sounded the alarm, but Mr. Potter is placing meat on the skeleton.  Listen carefully to what he is saying.  This will become an urgent situation without action.  The F-35 is behind schedule, so the DoD is rearranging the deck chairs.

The U.S. Defense Department is slowing Lockheed Martin Corp’s $300 billion F-35 fighter jet program, a multinational effort, to stabilize its schedule and costs, according to draft budget documents obtained by Reuters.

The department’s fiscal 2011 budget will request $10.7 billion to continue the F-35’s development and to procure 42 aircraft, a budget overview shows.

Overall, the plan is to cut planned purchases by 10 aircraft in fiscal 2011 and a total of 122 through 2015.

The Pentagon “has adjusted F-35 procurement quantities based on new data on costs and on likely orders from our foreign nations partners and realigned development and test schedules,” the document said without giving details.

“Stabilize its schedule and costs …”  This is a euphemism to indicates that the DoD won’t outspend the development capabilities of the program, and since the program is behind schedule, the development dollars will decrease.

All the while, aircraft are being retired, trained pilots are busy doing carpentry work on board their base, and as The Captain’s Journal pointed out, the F-35 has yet to log a single flying hour – even though it is supposed to be the cornerstone of the U.S. air fleet.  There is trouble in the air, and it isn’t of the sort that can be solved by wishful thinking about future weapons systems or flying gadgets that have yet to be designed or tested.  We told you so.

No comments yet.

RSS feed for comments on this post. TrackBack URL

Leave a comment


You are currently reading "F-35 Over Budget and Behind Schedule", entry #4455 on The Captain's Journal.

This article is filed under the category(s) Air Force,F-22,F-35 and was published January 27th, 2010 by Herschel Smith.

If you're interested in what else the The Captain's Journal has to say, you might try thumbing through the archives and visiting the main index, or; perhaps you would like to learn more about TCJ.

26th MEU (10)
Abu Muqawama (12)
ACOG (2)
ACOGs (1)
Afghan National Army (36)
Afghan National Police (17)
Afghanistan (704)
Afghanistan SOFA (4)
Agriculture in COIN (3)
AGW (1)
Air Force (41)
Air Power (10)
al Qaeda (83)
Ali al-Sistani (1)
America (22)
Ammunition (298)
Animals (312)
Ansar al Sunna (15)
Anthropology (3)
Antonin Scalia (1)
AR-15s (390)
Arghandab River Valley (1)
Arlington Cemetery (2)
Army (89)
Assassinations (2)
Assault Weapon Ban (29)
Australian Army (7)
Azerbaijan (4)
Backpacking (4)
Badr Organization (8)
Baitullah Mehsud (21)
Basra (17)
BATFE (244)
Battle of Bari Alai (2)
Battle of Wanat (18)
Battle Space Weight (3)
Bin Laden (7)
Blogroll (3)
Blogs (24)
Body Armor (23)
Books (3)
Border War (18)
Brady Campaign (1)
Britain (39)
British Army (36)
Camping (5)
Canada (18)
Castle Doctrine (1)
Caucasus (6)
CENTCOM (7)
Center For a New American Security (8)
Charity (3)
China (17)
Christmas (17)
CIA (30)
Civilian National Security Force (3)
Col. Gian Gentile (9)
Combat Outposts (3)
Combat Video (2)
Concerned Citizens (6)
Constabulary Actions (3)
Coolness Factor (3)
COP Keating (4)
Corruption in COIN (4)
Council on Foreign Relations (1)
Counterinsurgency (218)
DADT (2)
David Rohde (1)
Defense Contractors (2)
Department of Defense (217)
Department of Homeland Security (26)
Disaster Preparedness (5)
Distributed Operations (5)
Dogs (15)
Donald Trump (27)
Drone Campaign (4)
EFV (3)
Egypt (12)
El Salvador (1)
Embassy Security (1)
Enemy Spotters (1)
Expeditionary Warfare (17)
F-22 (2)
F-35 (1)
Fallujah (17)
Far East (3)
Fathers and Sons (2)
Favorite (1)
Fazlullah (3)
FBI (39)
Featured (192)
Federal Firearms Laws (18)
Financing the Taliban (2)
Firearms (1,847)
Football (1)
Force Projection (35)
Force Protection (4)
Force Transformation (1)
Foreign Policy (27)
Fukushima Reactor Accident (6)
Ganjgal (1)
Garmsir (1)
general (15)
General Amos (1)
General James Mattis (1)
General McChrystal (44)
General McKiernan (6)
General Rodriguez (3)
General Suleimani (9)
Georgia (19)
GITMO (2)
Google (1)
Gulbuddin Hekmatyar (1)
Gun Control (1,699)
Guns (2,386)
Guns In National Parks (3)
Haditha Roundup (10)
Haiti (2)
HAMAS (7)
Haqqani Network (9)
Hate Mail (8)
Hekmatyar (1)
Heroism (5)
Hezbollah (12)
High Capacity Magazines (16)
High Value Targets (9)
Homecoming (1)
Homeland Security (3)
Horses (2)
Humor (72)
Hunting (48)
ICOS (1)
IEDs (7)
Immigration (122)
India (10)
Infantry (4)
Information Warfare (4)
Infrastructure (4)
Intelligence (23)
Intelligence Bulletin (6)
Iran (171)
Iraq (379)
Iraq SOFA (23)
Islamic Facism (64)
Islamists (98)
Israel (19)
Jaish al Mahdi (21)
Jalalabad (1)
Japan (3)
Jihadists (82)
John Nagl (5)
Joint Intelligence Centers (1)
JRTN (1)
Kabul (1)
Kajaki Dam (1)
Kamdesh (9)
Kandahar (12)
Karachi (7)
Kashmir (2)
Khost Province (1)
Khyber (11)
Knife Blogging (7)
Korea (4)
Korengal Valley (3)
Kunar Province (20)
Kurdistan (3)
Language in COIN (5)
Language in Statecraft (1)
Language Interpreters (2)
Lashkar-e-Taiba (2)
Law Enforcement (6)
Lawfare (14)
Leadership (6)
Lebanon (6)
Leon Panetta (2)
Let Them Fight (2)
Libya (14)
Lines of Effort (3)
Littoral Combat (8)
Logistics (50)
Long Guns (1)
Lt. Col. Allen West (2)
Marine Corps (281)
Marines in Bakwa (1)
Marines in Helmand (67)
Marjah (4)
MEDEVAC (2)
Media (68)
Medical (146)
Memorial Day (6)
Mexican Cartels (45)
Mexico (69)
Michael Yon (6)
Micromanaging the Military (7)
Middle East (1)
Military Blogging (26)
Military Contractors (5)
Military Equipment (25)
Militia (9)
Mitt Romney (3)
Monetary Policy (1)
Moqtada al Sadr (2)
Mosul (4)
Mountains (25)
MRAPs (1)
Mullah Baradar (1)
Mullah Fazlullah (1)
Mullah Omar (3)
Musa Qala (4)
Music (25)
Muslim Brotherhood (6)
Nation Building (2)
National Internet IDs (1)
National Rifle Association (97)
NATO (15)
Navy (31)
Navy Corpsman (1)
NCOs (3)
News (1)
NGOs (3)
Nicholas Schmidle (2)
Now Zad (19)
NSA (3)
NSA James L. Jones (6)
Nuclear (63)
Nuristan (8)
Obama Administration (222)
Offshore Balancing (1)
Operation Alljah (7)
Operation Khanjar (14)
Ossetia (7)
Pakistan (165)
Paktya Province (1)
Palestine (5)
Patriotism (7)
Patrolling (1)
Pech River Valley (11)
Personal (74)
Petraeus (14)
Pictures (1)
Piracy (13)
Pistol (4)
Pizzagate (21)
Police (669)
Police in COIN (3)
Policy (15)
Politics (990)
Poppy (2)
PPEs (1)
Prisons in Counterinsurgency (12)
Project Gunrunner (20)
PRTs (1)
Qatar (1)
Quadrennial Defense Review (2)
Quds Force (13)
Quetta Shura (1)
RAND (3)
Recommended Reading (14)
Refueling Tanker (1)
Religion (497)
Religion and Insurgency (19)
Reuters (1)
Rick Perry (4)
Rifles (1)
Roads (4)
Rolling Stone (1)
Ron Paul (1)
ROTC (1)
Rules of Engagement (75)
Rumsfeld (1)
Russia (37)
Sabbatical (1)
Sangin (1)
Saqlawiyah (1)
Satellite Patrols (2)
Saudi Arabia (4)
Scenes from Iraq (1)
Second Amendment (704)
Second Amendment Quick Hits (2)
Secretary Gates (9)
Sharia Law (3)
Shura Ittehad-ul-Mujahiden (1)
SIIC (2)
Sirajuddin Haqqani (1)
Small Wars (72)
Snipers (9)
Sniveling Lackeys (2)
Soft Power (4)
Somalia (8)
Sons of Afghanistan (1)
Sons of Iraq (2)
Special Forces (28)
Squad Rushes (1)
State Department (23)
Statistics (1)
Sunni Insurgency (10)
Support to Infantry Ratio (1)
Supreme Court (77)
Survival (211)
SWAT Raids (57)
Syria (38)
Tactical Drills (38)
Tactical Gear (17)
Taliban (168)
Taliban Massing of Forces (4)
Tarmiyah (1)
TBI (1)
Technology (21)
Tehrik-i-Taliban (78)
Terrain in Combat (1)
Terrorism (96)
Thanksgiving (13)
The Anbar Narrative (23)
The Art of War (5)
The Fallen (1)
The Long War (20)
The Surge (3)
The Wounded (13)
Thomas Barnett (1)
Transnational Insurgencies (5)
Tribes (5)
TSA (25)
TSA Ineptitude (14)
TTPs (4)
U.S. Border Patrol (8)
U.S. Border Security (22)
U.S. Sovereignty (29)
UAVs (2)
UBL (4)
Ukraine (10)
Uncategorized (104)
Universal Background Check (3)
Unrestricted Warfare (4)
USS Iwo Jima (2)
USS San Antonio (1)
Uzbekistan (1)
V-22 Osprey (4)
Veterans (3)
Vietnam (1)
War & Warfare (426)
War & Warfare (41)
War Movies (4)
War Reporting (21)
Wardak Province (1)
Warriors (6)
Waziristan (1)
Weapons and Tactics (79)
West Point (1)
Winter Operations (1)
Women in Combat (21)
WTF? (1)
Yemen (1)

August 2025
July 2025
June 2025
May 2025
April 2025
March 2025
February 2025
January 2025
December 2024
November 2024
October 2024
September 2024
August 2024
July 2024
June 2024
May 2024
April 2024
March 2024
February 2024
January 2024
December 2023
November 2023
October 2023
September 2023
August 2023
July 2023
June 2023
May 2023
April 2023
March 2023
February 2023
January 2023
December 2022
November 2022
October 2022
September 2022
August 2022
July 2022
June 2022
May 2022
April 2022
March 2022
February 2022
January 2022
December 2021
November 2021
October 2021
September 2021
August 2021
July 2021
June 2021
May 2021
April 2021
March 2021
February 2021
January 2021
December 2020
November 2020
October 2020
September 2020
August 2020
July 2020
June 2020
May 2020
April 2020
March 2020
February 2020
January 2020
December 2019
November 2019
October 2019
September 2019
August 2019
July 2019
June 2019
May 2019
April 2019
March 2019
February 2019
January 2019
December 2018
November 2018
October 2018
September 2018
August 2018
July 2018
June 2018
May 2018
April 2018
March 2018
February 2018
January 2018
December 2017
November 2017
October 2017
September 2017
August 2017
July 2017
June 2017
May 2017
April 2017
March 2017
February 2017
January 2017
December 2016
November 2016
October 2016
September 2016
August 2016
July 2016
June 2016
May 2016
April 2016
March 2016
February 2016
January 2016
December 2015
November 2015
October 2015
September 2015
August 2015
July 2015
June 2015
May 2015
April 2015
March 2015
February 2015
January 2015
December 2014
November 2014
October 2014
September 2014
August 2014
July 2014
June 2014
May 2014
April 2014
March 2014
February 2014
January 2014
December 2013
November 2013
October 2013
September 2013
August 2013
July 2013
June 2013
May 2013
April 2013
March 2013
February 2013
January 2013
December 2012
November 2012
October 2012
September 2012
August 2012
July 2012
June 2012
May 2012
April 2012
March 2012
February 2012
January 2012
December 2011
November 2011
October 2011
September 2011
August 2011
July 2011
June 2011
May 2011
April 2011
March 2011
February 2011
January 2011
December 2010
November 2010
October 2010
September 2010
August 2010
July 2010
June 2010
May 2010
April 2010
March 2010
February 2010
January 2010
December 2009
November 2009
October 2009
September 2009
August 2009
July 2009
June 2009
May 2009
April 2009
March 2009
February 2009
January 2009
December 2008
November 2008
October 2008
September 2008
August 2008
July 2008
June 2008
May 2008
April 2008
March 2008
February 2008
January 2008
December 2007
November 2007
October 2007
September 2007
August 2007
July 2007
June 2007
May 2007
April 2007
March 2007
February 2007
January 2007
December 2006
November 2006
October 2006
September 2006
August 2006
July 2006
June 2006
May 2006

about · archives · contact · register

Copyright © 2006-2025 Captain's Journal. All rights reserved.